Households and businesses along the East Bank of Demerara could benefit from a major upgrade to the electricity transmission network, with Guyana Power and Light (GPL) signing an US$11.4 million contract to replace two ageing power lines that have been operating for more than three decades.
The contract, signed on November 12, covers the replacement of transmission lines L1 and L3 between the Garden of Eden and Golden Grove substations, a section of the network that plays an important role in moving electricity to customers along the East Bank.
The project involves approximately 11 kilometres of new 69-kilovolt overhead transmission lines and is expected to introduce a double-circuit configuration, along with fibre-optic cables to improve fault detection and monitoring.
The contract was awarded to the CRIG–DINGLI Joint Venture, comprising China Railway International Group and Henan Dingli Power Equipment.
For customers, the significance of the investment lies in the condition of the existing infrastructure and the need to strengthen a transmission network that must accommodate Guyana's growing electricity demand.
The two lines have been in service for more than 30 years, making their replacement an important part of efforts to modernise the country's electricity system and reduce the risks associated with ageing infrastructure.
While the installation of new lines does not automatically guarantee an end to outages, a stronger transmission network can help improve the movement of electricity, limit disruptions associated with equipment failures and provide greater flexibility in managing the grid.
The use of fibre-optic technology is also expected to improve the monitoring of the lines, allowing operators to identify faults more efficiently and respond to problems affecting the network.
The upgrade forms part of the Strengthening Energy Matrix Diversification Programme, which receives partial financing from the Inter-American Development Bank (IDB).
Beyond replacing ageing infrastructure, the programme is intended to strengthen the electricity network to accommodate additional generation capacity and support the integration of renewable energy sources.
That is increasingly important as Guyana works to expand its electricity supply through several major energy projects while preparing the grid for higher demand from households, businesses and new industries.
However, generating more electricity is only part of the challenge. The transmission and distribution infrastructure must also be capable of moving that electricity reliably to consumers.















.png)